Categories:
Nelson Crescent Lesmurdie thumbnail

  February 2024

  • First Floor internal ceilings & plastering are being installed 
  • First Floor glazing is now completed & the front elevation is being textured
  •  

  January 2024

  • The concrete roof slab has been poured, cured & formwork has been stripped & removed 
  • The Roof Slab is now waterproofed
  • FF electrical, aircon tubes have been completed & internal plaster has commenced

  December 2023

  • We have loaded the First Floor bricks & completed the First Floor concrete walls & built the First Floor internal brickwork
  • The Concrete slab roof has been formed up, reinforcing installed & all prelays completed & will be poured on the 21/12

  November 2023

  • The First Floor slab has been poured & First Floor external concrete walls are now completed & we are starting the First Floor brickwork
  • Concrete roof slab will be formed, poured & curing over Dec / Jan

  October 2023

  • The Ground Floor walls are complete & the garage walls have been backfilled
  • Pool has been installed & the surrounding limestone poured & sealed

  September 2023

  • The Ground Floor suspended slab has been poured & external concrete walls poured
  • Pool has been lifted in & installed & the slab is being honed ready for brickwork

  August 2023

  • Earthworks, backfilling & compacting is progressing
  • Leach drains have been installed
  • Ground floor & suspended slab formwork has been completed & the pool base has been poured
  •   

   July 2023

  • Earthworks, rock breaking, forming & pouring the basement retaining footings & walls are well underway.  
  • We have stripped the completed walls, waterproofed them & backfilling is in progress

   June 2023

  • We have received our Build Permit from the shire & mobilised on site
  • Earthworks have commenced & we are progressing well with rock breaking, forming & pouring the basement footings & have commenced the concrete walls

May 2023

  • We have the “go ahead” from our Client now & have submitted the working drawings to shire for Building Permit 
  • Earthworks are scheduled to commence early June & when confirmed we can create a timeline & create a site work schedule                                                                                                                            

April 2023

  • We are awaiting the “go ahead” from our Client to submit the drawings to shire for Building Approval & then we can create a timeline & commence site works.

March 2023

  • We are awaiting the “go ahead” from our Client to submit the drawings to shire for Building Licence & then we can create a timeline & commence site works.

February 2023

  • We are in the final stages of completing our scheduling / quoting and are working with our Client to submit to shire for building licence approval with the aim of commencing work on site in March.

January 2023

  • We have completed an amazing concept design for our Client for their new luxury custom home on a very challenging block with incredible City views and have submitted the drawings to the shire for D.A. approval.
  • Architectural Working drawings, structural engineering and interior design selections are now completed.
  • Currently, we are scheduling and quoting the works and aim to provide this to our Client mid-Feb with the aim of commencing on-site in March.

December

  • We have now received D.A approval 
  • Architectural Working drawings , structural engineering and interior design selections have been completed.
  • Early Jan 2023 we will begin our costings and provide to our Client mid-February

November 

  • Jan 2023 we will start our costings and provide to our Client

October 

  • We have completed an amazing concept design for our Client for their new home on a very challenging block with incredible City views and have submitted the drawings to shire for D.A approval 
  • Architectural Working drawings , structural engineering and interior design selections are progressing well and our goal is to have the documentation completed late December


September 

  • We have completed an amazing concept design for our client on a new home, located on a very challenging block with incredible city views. We have submitted the drawings to the shire for D.A approval.




Back to top arrow